Phuket Property Investment and Infrastructure 2026–2031: Expressway, Tram and Airport Plans

For Phuket property investment, the three big transport plans are at different stages. The Kathu–Patong expressway has a target opening date, but its revised design still needs Cabinet approval. MRTA is still studying how to fund the airport–Chalong tram, and the airport’s next expansion was last reported in design. None of them had started construction when we checked.

Status checked on 22 November 2026.

Which Phuket Infrastructure Projects Are Approved, Funded or Only Proposed?

Large public projects in Thailand pass through several steps, such as studies, design, Cabinet approval, tender and construction. The table shows where five Phuket plans stood when we checked.

ProjectStageCabinet approval for current planSource
Expressway Phase 1, Kathu–PatongRevised design sent to the Transport Ministry; land acquisition under wayNot yet; expected around December 2026Nation Thailand and others, September 2026
Expressway Phase 2, Mueang Mai–Ko Kaeo–KathuDetailed designNot yet; sought in 2027Nation Thailand and others, September 2026
Tram Phase 1, Airport–ChalongFeasibility review and PPP reportNot yet; the investment model is still being studiedMRTA project page, read November 2026
Airport Phase 2Design stageNot yet; on the Transport Ministry’s list for CabinetNation Thailand, May and July 2026
Andaman Airport, Phang NgaFeasibility studyNoNation Thailand, May 2026

“Funded” is the hardest label to give. In August 2025 the Cabinet approved a model in which the Expressway Authority of Thailand (EXAT) builds Phase 1 itself, paid for by borrowing or bonds with Finance Ministry support. That decision was for the 2025 design, which has since changed twice. For the tram, MRTA is still studying which investment model to use.

Simple timeline diagram with five horizontal bars of different lengths on a plain background, with no labels, numbers or logos

Where Does the Kathu–Patong Expressway Stand?

EXAT plans the Phuket Expressway in two phases: Phase 1 from Kathu to Patong, 3.98 km, and Phase 2 from Mueang Mai to Ko Kaeo and Kathu, 30.62 km. It is meant to take pressure off Thepkrasattri Road and Phra Barami Road, the main route from Kathu over the hill to Patong.

The design has changed more than once since the Cabinet’s August 2025 decision, most recently to a narrower tunnel of about 14 m. Our tunnel guide, linked below, has the full history.

In mid-September 2026, reports said EXAT had sent the revised Phase 1 to the Transport Ministry, with Cabinet consideration expected around December 2026. The schedule given was construction from October 2027 for about four years and opening in October 2031. Phase 2 was in detailed design, with Cabinet approval to be sought in 2027. In July 2026 Phase 2 was also on a Transport Ministry list of projects being prepared for Cabinet approval.

EXAT’s own projection is that the Kathu–Patong drive of about 30 minutes would take about five through the tunnel. That figure covers the tunnel section only. Our Kathu–Patong tunnel guide for Karon has the route, design history and what it could mean for trips from Karon.

What Happened to the Phuket Tram?

The tram is the Phuket Mass Transit System. The Mass Rapid Transit Authority of Thailand (MRTA) describes Phase 1 as a light rail or low-floor tram line of 42.0 km with 21 stations, from Phuket International Airport along Highway 402 through Phuket Town to the Chalong Five-Way Intersection. The route does not run along the west coast.

In January 2026 the Transport Minister denied reports that the project had been scrapped. He said it remains government policy but will only go ahead after the island’s main road bottlenecks are fixed, starting with the Patong tunnel, and that electric buses would first run along the future tram corridor.

MRTA’s project page, read on 22 November 2026, lists the current status as reviewing the feasibility study and preparing the PPP report. The same page shows MRTA’s planned dates for Cabinet approval, construction and opening, so check it for the latest schedule.

The MRTA project page is the place to check for updates.

Is Phuket Airport Expanding?

Airports of Thailand (AOT) plans a second development phase at Phuket International Airport. The Nation reported in May 2026 that it would expand the international terminal and utility systems, adding capacity for 5.5 million passengers a year and taking the total to at least 18 million. The project was in the design stage. AOT was also studying a new Andaman Airport in Phang Nga.

In July 2026 the Transport Ministry listed Phuket Airport Phase 2 among 20 projects it was preparing for Cabinet approval. We found no report of a Cabinet decision by 22 November 2026.

Read the Nation Thailand report on AOT’s expansion plans for the full list of airports. For getting to the airport today, see our Karon to Phuket Airport transport guide.

Illustration of a modern airport terminal with a curved roof and a parked aircraft at the gate, seen from the apron at dusk, with no airline colours or text

What Do These Plans Mean for Phuket Property Investment?

We make no forecast about how any of these projects will affect property prices or rents. What the record shows is how often the dates move. The expressway’s opening target was 2030 in EXAT’s March 2025 material, and is October 2031 in the September 2026 reports.

Some practical points for buyers:

  • Base your numbers on the roads, airport and services that exist today, and treat new infrastructure as a possible later change.
  • If a sales pitch mentions a tram stop or an expressway, ask for the project’s current stage and a dated official source.
  • Building work of about four years, as reported for the Patong tunnel, can mean diversions near the site. Ask how close a property is to any planned route.
  • Check where a route actually runs. The planned tram line goes through Phuket Town to Chalong, not along the west-coast beaches.

For the wider picture of the market in Karon, read our Phuket property market 2026 outlook for Karon buyers.

How Can You Follow These Projects Yourself?

  • MRTA’s Phuket project page shows the tram route and current plans.
  • EXAT runs a project website for the Phuket Expressway, linked from its main site.
  • Cabinet decisions are reported by the government and by The Nation, the Bangkok Post and The Phuket News.

Look for three things in any update: who decided, what exactly they approved, and the date.

Frequently Asked Questions

When will the Patong tunnel open?

The latest reports, from September 2026, give October 2031 as the target, subject to Cabinet approval expected around December 2026. Treat the date as a target.

Has the Phuket tram been cancelled?

No. In January 2026 the Transport Minister said it remains government policy but will follow road improvements. MRTA’s project page lists its current status and schedule.

Does the planned tram go to Karon?

No. MRTA’s Phase 1 route runs from the airport through Phuket Town to the Chalong Five-Way Intersection.

Is Phuket getting a new airport?

AOT is studying the feasibility of an Andaman Airport in Phang Nga. It is a study, with no approval reported.

Will these projects raise property prices in Karon?

We do not forecast prices. Base a purchase on what exists today, and check the stage and date of any project a seller mentions.

Final Takeaway

On 22 November 2026, none of Phuket’s three headline transport plans had Cabinet approval for its current design. The expressway is expected at Cabinet first, the airport expansion was last reported in design, and the tram is still under study. Judge any Phuket property investment on today’s access, and follow the official sources for change.

To talk through location and access for Ever Prime Residences in Karon, contact the Ever Prime Residences team.

This article is general information, not financial, tax or legal advice. Returns are not guaranteed.

Image note: The images in this article are illustrations. They do not show Ever Prime Residences or any real document, project or place.